Crews continue to work on sidewalk and new ramps throughout Shawnee.

• Crews are working at 10th and Union in Shawnee.

• This is part of the city’s Sidewalk/ADA Handicap Ramp Project.

• All Roads Paving was awarded the contract for this year.

• City Engineer John Krywicki said the contract totaled $127,337.25 for a number of these projects.

• He said year’s contract is approximately 35 percent spent,

• The contract documents allow for the contract to be extended for one additional year period.

• That is if both the City and the Contractor agree the same unit prices would be acceptable.

• He said it’s an ongoing project.

• The city tries to budget $150,000 to 200,000 each year for installation of the accessible ramps.