  • Kickapoo Reconstruction project

  • Kickapoo project progressing, water line relocation about 90 percent finished.
    • email print
  • The Details:
     
    • City Engineer John Krywicki says waterline line relocation is about 90 percent complete on the Kickapoo reconstruction.
    • He says the water line relocation will continue across MacArthur terminating just immediately before it gets to 32nd Street.
    • That is one block north of MacArthur.
    • Work continues on the paving construction from the Spur to Independence on the southbound lanes.
    • When those two lanes are completed in approximately 3 or so weeks, then traffic will be moved onto them.
    • Construction on the two northbound lanes will begin from the Spur to Independence.
    • He estimates overall over all, the contractor is probably 7-8 percnt complete with paving construction.
    • He said tentative completion timeframe probably not until early Fall 2014.
    • Total construction bid price was $11,274,639 by Haskel Lemon Construction.
    • That includes all the water line relocation costs of $1,765,813.
     
     
     
     