Project is reportedly about 30 percent complete.

The Details:

• Assistant City Engineer Michael Ludi reports the Kickapoo project is currently 30 percent complete.

• He says 40 percent of the contracted time has been used.

• The asphalt work here is laying a temporary widening of the road.

• This will allow both the north and south bound traffic to be moved.

• It will be moved onto the east side of the road.

• The crews will then remove the west half of the road.

• This phase of the project will remove the west half of the road.

• It will be removed from Cammack Streeet south to Independence Street.